Project Description
Powell Valley Elementary
The bond will fund the following improvements to the school:
Upgrades to heating system, roof, flooring, and other needed building repairs
Internally locking door hardware at all classrooms
Secure front entry and office modifications
Updated furnishings and equipment for classrooms
New low voltage systems (intercoms, fire alarms, cameras, and emergency power)
Technology upgrades and wireless infrastructure in all classrooms
Bus/parent pick-up/drop-off separation
New playground equipment and surfacing
Click HERE for more information and overview of improvements to Powell Valley ES
Click HERE for a Powell Valley ES Site Map

Home of the Panthers
Becca VandeWalle – Project Manager
503.415.0468
beccav@cornerstonemgi.com
Steven Eggleston – Architect
503.284.0988
StevenE@axisdesigngroup.com
Craig Shearmire – Contractor
Brockamp & Jaeger, Inc.
craigs@brockamp-jaeger.com
503.655.9151
GBSD Community Relations
503-261-4558
gbsd@gresham.k12.or.us
Small Project Schedule:
2018 | 2019 | 2020 | 2021 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||
J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | |||||||||||||
Pre-Design / Design / Bid-Award | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Construction / Closeout 21 Months |
Legend
Pre-Design | Design | Bid-Award | Construction | Land Use | Closeout |