Project Description
North Gresham Elementary
Project Updates
Thanks to all who attended our North Gresham Elementary School Dedication Ceremony this October.
Check out this video highlighting the beautiful new North Gresham Elementary campus.
September 2019
Construction is complete on the new North Gresham Elementary School; the building opened to students this September.
- This building replaces the old North Gresham campus, which was first built in 1960.
- The new building has 73,500 square feet and 30 new classrooms, each with a 70-inch interactive flat panel touch screen for a modern education.
- The new North Gresham includes a modern secure vestibule entrance to increase school safety, as well as internally locking doors in every classroom.
- The gymnasium includes a full-sized basketball court
- The new cafeteria and library are designed to maximize natural light. The new music room is built on the stage, with a movable wall that allows performances with audiences seated in the gymnasium.
- Renee Alexander, the architect of the new NGES campus, is a North Gresham alum, and the building is
designed for a capacity of up to 550 students
North Gresham will be holding a Dedication Ceremony on the evening of October 15. Stay tuned for more details.
July 2019
Bremik Construction recently shared with us some new aerial photographs of the construction progress at the new North Gresham campus.
June 2019
The exterior facade of the new campus is almost complete, with only a few metal panels left to install. Crews have nearly finished the playground, and site work around the school (pouring concrete for the new parking lot) will continue throughout the month. With class almost out, crews are preparing to begin the second phase of the project, which entails tearing down the old structure and replacing it with ball fields. Photographs courtesy of Bremik Construction:
February 2019
Significant progress is underway at the North Gresham Elementary School site. The interior walls have been framed, and the covered play area, covered walkway, and ball walls (for recess games) are complete. Crews have begun to install the outer brick facade, and the interior drywalling will begin in the next few weeks. Here are some photos taken by Bremik Construction’s drone photographer.
December 2018
Concrete slabs for the first floor are completely installed, and we are continuing to connect the walls together with steel beams. Concrete is being poured for the second floor of the facility, which will include classrooms and the North Gresham library. The HVAC ducts are also being installed. These photos below were taken when the Bond Oversight Committee visited the campus for a tour before their quarterly meeting.
Mid November 2018
The tilt wall panels have been completely installed. Construction crews have also finished installing the structural steel columns throughout the interior of the building. Crews are currently finishing pouring the concrete slab to support the tilt panels, and installing new roof joists and the roof deck of the building.
Early November 2018
Bremik Construction has begun erecting the walls of the new North Gresham Elementary School. Check out the video below.
October 2018
Construction crews finished building the foundation for the new school this summer. the new North Gresham Elementary school structure will be built using a tilt-up structure. Construction crews spent this month pouring concrete into wall frames while lying on the ground, and using a crane to tilt the walls up and secure them into place. It took three days to pour all 56 wall panels. Walls are being erected this final week of October, and construction crews will begin building the steel braces that support the roof and second floor this November.
Bremik Construction provided these aerial photos.
August 2018
Crews have begun pouring concrete for the foundation of the new school.
July 2018
Construction crews have begun preparing to pour concrete for the foundation of the new campus.
April 2018
The North Gresham Elementary School community celebrated the beginning of construction on the new school with a groundbreaking ceremony. Construction begins this spring and the new building will be open to students in time for the beginning of the 2019-2020 school year.
October 2017
Representatives from BBT Architects provided an update of the North Gresham ES project to the Bond Oversight Committee. The slides from their presentation are available HERE.
June 2017
the design team convened a neighborhood meeting to review the proposed project goals, scope, timeline and impacts.

About the Project – Planned Improvements
The North Gresham Elementary community will be getting an entire new elementary school in time for the 2019/2020 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.
The guiding principles of the design are:
“A beautiful, inviting and safe school that supports learning and includes unique spaces that invoke a special sense of pride”
Based on these guiding principals the design team has focused on 4 key improvement areas for the new North Gresham Elementary School:
- Better Student Flow: Create a dynamic school with classroom and grade layouts the facilitates collaboration and learning.
- Daylight and HVAC systems: Studies have shown these are key factors in improving learning environments.
- Improved Learning Environment: Consistent and right-sized learning spaces with modern technology.
- Safety and security improvements: This includes secured entry to play fields and playground as well as a secured entry and vestibule.
- Separation of Music and Gym
- Community Interaction with Building: Improved bus parking and parent pick up
Community and Stakeholder Involvement
North Gresham Elementary Staff and Stakeholder Planning
At the request of the district, Principal Tracy Klinger convened school district advisory group (SDAT) as well as a several focus groups made up of NGES teachers, parents, staff and stakeholders to advise the district on their needs, desire and priorities for the NGES bond project. These teams have spent numerous hours working with the architects and construction management team to provide important feedback as the design phase of the project has progressed.
Live Camera

Home of the Stars
Principal:
Tracy Klinger
Project Manager:
Emil Hameed
Cornerstone Management
emilh@cornerstonemgi.com
503-539-2245
Architect:
Renee Alexander
BBT Architects
ralexander@bbtarchitects.com
541-382-5535
Contractor:
Bob Trapa
Bremik Construction
BT@Bremik.com
503-688-1000
GBSD Community Relations
503-261-4558
gbsd@gresham.k12.or.us
Project Schedule
2017 | 2018 | 2019 | 2020 | 2021 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | D | |
Pre-Design / Design / Bid-Award | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Construction / Closeout 21 Months |
Legend
Pre-Design | Design | Bid-Award | Construction | Land Use | Closeout |