Hollydale Elementary School2019-10-19T01:40:45+00:00

Project Description

Hollydale Elementary School

Construction Update: October 2019

Thanks to Bremik Construction for sharing these photos! Brickwork on the exterior of the building has been complete on the new extension of the building. Drywall and door framing has also been completed, as well as the plumbing, ducting, and electricity. Crews are currently adding whiteboard, tackboards, cabinets, bathroom sinks, and bathroom faucets. Exterior landscaping will begin soon.

Construction Update – July 2019

 

Construction progress remains on schedule for the improvements at Hollydale Elementary. All six new classrooms are slated to be complete by this upcoming winter, and the improvements and renovations to the existing campus are on schedule for completion before students arrive in the building this September. Crews have removed carpet, installed a new secured entrance vestibule at the front of the building, installed a new generator, and polished concrete floors across the campus.

April 2019

Thanks to all who came out for our Groundbreaking Ceremony this month! Construction begins this spring to add six new classrooms to the Hollydale campus.

July 2018

Thanks to all who came out to attend our ribbon cutting ceremony for the new playground at Hollydale Elementary! Students seem pretty excited about the new play structure.

The bond will fund the following improvements to the school:

  • Upgrades to heating and cooling systems, roof, flooring, and other needed building repairs

  • Internally locking door hardware at all classrooms

  • Secure front entry and office modifications

  • Updated furnishings and equipment for classrooms

  • New low voltage systems (intercoms, fire alarms, cameras, and emergency power)

  • Technology upgrades and wireless infrastructure in all classrooms

  • New playground equipment and surfacing

  • Expansion for capacity

Home of the Hollydale Heroes

GBSD Community Relations
503-261-4558
gbsd@gresham.k12.or.us

Schedule:

2017 2018 2019 2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Pre-Design / Design / Bid-Award
Construction / Closeout 21 Months

Legend

Pre-Design Design Bid-Award Construction Land Use Closeout