North Gresham Elementary2018-08-10T21:33:11+00:00

Project Description

North Gresham Elementary

About the Project – Planned Improvements

The North Gresham Elementary community will be getting an entire new elementary school in time for the 2019/2020 school year. This is an excited opportunity for students, staff, parents and community to shape the future of their neighborhood school for years to come.

The guiding principles of the design are:

“A beautiful, inviting and safe school that supports learning and includes unique spaces that invoke a special sense of pride”

Based on these guiding principals the design team has focused on 4 key improvement areas for the new North Gresham Elementary School:

  • Better Student Flow: Create a dynamic school with classroom and grade layouts the facilitates collaboration and learning.
  • Daylight and HVAC systems: Studies have shown these are key factors in improving learning environments.
  • Improved Learning Environment: Consistent and right-sized learning spaces with modern technology.
  • Safety and security improvements: This includes secured entry to play fields and playground as well as a secured entry and vestibule.
  • Separation of Music and Gym
  • Community Interaction with Building: Improved bus parking and parent pick up

Project Updates

August 2018

Crews have begun pouring concrete for the foundation of the new school.

July 2018

Construction crews have begun preparing to pour concrete for the foundation of the new campus.

April 2018

The North Gresham Elementary School community celebrated the beginning of construction on the new school with a groundbreaking ceremony. Construction begins this spring and the new building will be open to students in time for the beginning of the 2019-2020 school year.

October 2017

Representatives from BBT Architects provided an update of the North Gresham ES project to the Bond Oversight Committee. The slides from their presentation are available HERE.

June 2017

the design team convened a neighborhood meeting to review the proposed project goals, scope, timeline and impacts.

Community and Stakeholder Involvement

North Gresham Elementary Staff and Stakeholder Planning

At the request of the district, Principal Tracy Klinger convened school district advisory group (SDAT) as well as a several focus groups made up of NGES teachers, parents, staff and stakeholders to advise the district on their needs, desire and priorities for the NGES bond project. These teams have spent numerous hours working with the architects and construction management team to provide important feedback as the design phase of the project has progressed.

Home of the Stars

Principal:

Tracy Klinger

Project Manager:

Emil Hameed
Cornerstone Management
emilh@cornerstonemgi.com
503-539-2245

Architect:

Renee Alexander
BBT Architects
ralexander@bbtarchitects.com
541-382-5535

Contractor:

Bob Trapa
Bremik Construction
BT@Bremik.com
503-688-1000

GBSD Community Relations
503-261-4558
gbsd@gresham.k12.or.us

Project Schedule

2017 2018 2019 2020 2021
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Pre-Design / Design / Bid-Award
Construction / Closeout 21 Months

Legend

Pre-Design Design Bid-Award Construction Land Use Closeout